Kashagan: key to Kazakhstan’s future

Once it comes on stream, the giant Kashagan field will establish Kazakhstan as a major oil exporter, says Oliver Adderley

AS KAZAKH AUTHORITIES grapple with the global  recession, politicians and bankers privately comment that things would look a lot different had the  Kashagan project come on stream as planned in  2008. This is because Kashagan, the huge 38 billion  barrel offshore ‘elephant field’, in shallow waters  some 70km south of the city of Atyrau, will double  the country’s oil production to more than 3 million  barrels a day within a few years of coming on stream  in the last quarter of 2012 or early 2013.

That will mean a huge ongoing boost to the  country’s export income and a shot in the arm for  government revenues big enough, and durable enough, to transform the country’s balance of payments and  turn the country into a net capital exporters.

At last year’s annual Kioge oil and gas conference  in Almaty, Energy Minister Sauat Mynbaev  summarised the outcome of many months of often  fraught negotiations between the government and  the consortium of international oil companies developing the Kashagan project. In return for  pledges of heavy continuing investment by the oil companies, and a deal to double the shareholding  of state energy corporation KazMunaiGaz (KMG),  the government, he said, reluctantly accepted both  higher cost estimates and a new timetable for first oil, which will now start to flow eight years later than the original target date of 2005.

The negotiations were sparked off by the oil  companies’ admission, two years earlier, that costs  had once again spiralled way beyond previous  estimates and that another five years of heavy  investment were required before oil could start to  flow safely from the offshore field to the onshore  processing facilities at Eskene, north of Atyrau.

The government accepted that a large part of the  cost inflation reflected the steep rise in global prices  for steel and other key construction materials and  the competition for scarce and expensive drilling  rigs and specialist services, as oil prices soared to  a peak of $147 a barrel in July 2007. Kashagan was  especially exposed to cost inflation because of the  huge logistical difficulties involved in getting men  and equipment to the offshore site of what one senior oil man describes as “the most complex engineering  project in the world”.

Even so, the rise in ‘life of project’ costs from an  originally estimated $29 billion to $136 billion has  been eye-watering and forced the oil companies  themselves to review their own shortcomings over  the first years of the project. But with so much money already sunk in the project, and so much hanging  on a successful outcome, the government finally  agreed to accept the higher estimates, after imposing financial penalties and a deal under which KMG  emerged as a co-equal in the consortium set up to  exploit the field. The two sides also agreed that first  oil production of around 150,000 barrels a day (b/d)  would start flowing from the offshore production  platforms in the last quarter 2012, or early 2013.

The fact that the initial flow will be both later and  only a third of the originally expected 450,000 b/d  is compensated for by a major up-rating of the full  regime flow, which is now scheduled to rise to 1.5  million b/d before the end of the decade and stay that way for at least two decades.

But for that to happen, several billions of dollars  worth of drilling and processing equipment still have to be installed and all concerned have to be absolutely sure that the deadly sulphurous gas associated  with the oil can be re-injected safely into the field  5km below the shallow Caspian Sea at super- high pressure. The fact that similar techniques  have already been successfully introduced at the  onshore Tengiz and Karachaganak fields, which  are geologically similar in key respects, has raised  confidence in a successful outcome.

The government was not the only party to be  dissatisfied with slow progress at Kashagan since  commercial quantities of oil were confirmed in  the summer of 2000. Shareholders and senior  management of the oil companies have been even  more dismayed at the prospect of another five years  of investing around $3 billion a year without a return on the investment until 2013.

Confirmation that the bone-shaped field, some  75km long and up to 45km wide, was indeed one  giant structure triggered the go-ahead for the first  stage of a project which, at the time, was expected to cost around $10 billion and produce first oil by 2005,  although that date was only reluctantly agreed by the oil companies in the face of heavy political pressure  for an early date.

The unhappiness of both government and the oil  companies with the delays and spiralling costs since  then meant that last year’s protracted government/ consortium negotiations were as much a forensic  examination of what had gone wrong for the oil  companies as for the governments

Painfully, members of the AGIP-KCO consortium  set up to manage the project in 2000 came to the  conclusion that much of the blame lay with the way  the oil companies themselves had underestimated  the technical and logistical challenges and cobbled  together a compromise solution to the big question  of who would be in charge of operating the project.  France’s Total made clear it would not accept  management control passing to Exxon, and the  US company was adamant it would not be pushed  around by the French. Shell was preoccupied with  other problems. In the end, Italy’s ENI was chosen as  operator as the compromise candidate acceptable to  the other three members of the ‘big four’ stakeholders.

The ‘big four’ were ENI, Exxon-Mobil, Shell and  Total. They each held an 18.5 per cent stake in the  consortium alongside smaller shareholders Conoco- Phillips, Japan’s Inpex and the Kazakh state energy  corporation KMG. After passing what was soon  to become a poisoned chalice to ENI’s operating  company, AGIP, and setting up the AGIP-KCO  consortium, the other oil majors failed to put in the top-level managerial and technical talent needed to supplement ENI’s own technical and other skills. The oil majors had only formed a consortium  because the task of developing a massive oil deposit in a greenfleld offshore site, with huge climatic,  logistical and safety challenges, at the frontier  of several advanced technologies was clearly way  beyond the resources of any one of them on their  own. But although Italy’s privatised former state  oil company is a global operator, it has nothing like the deep pockets, managerial depth and technical  expertise in deep and offshore drilling of its bigger  partners. Given the scale of the task, each of the  partners should have put in their best people and  applied their most developed technology to the  project – but they didn’t, leaving ENI to struggle  with a task beyond its capabilities. The shallow upper Caspian Sea, where Kashagan  lies, is ice-bound for more than four months a year,  while the main access to the inland sea is through  the Russian canal and river system, which is also  ice-bound for months, or the over-stretched Russian  road and rail system. The alternative is a complex  multi-nodal passage involving several transhipments  from Bulgarian or Romanian ports across the Black  Sea to the Georgian ports of Poti or Batumi, and then by road or rail across Georgia and Azerbaijan to Baku. Only from Baku can cargoes be shipped across the  Caspian to ice-free Aktau or the Kashagan supply base at Bautino all year round.

This logistical nightmare gives the consortium  only a six-month window each year through which  to funnel outsized cargoes too big for road or rail.  Another serious problem has been obtaining visas  and work permits for the key foreign personnel  needed to push forward such a complex, high-  tech project. With highly specialised engineers  costing up to $18,000 a day to hire, any delay proved  hugely expensive.

Any failure to get men and equipment on-site as the weather window opened added hugely to costs. But  so did major mistakes, such as under-estimation of  the number of drilling islands that were needed and  the location of offshore accommodation modules too ^ close to production areas. These had to be expensively re-located away from the wells in view of the extra- stringent health and safety rules in force at all the  deep, sub-salt oil and gas projects in the region.

The toughest rules are required because of the  deadly nature of the hydrogen sulphide and other  poisons that make up more than 17 per cent of  the hot, sour and corrosive gas which reaches  the surface together with the oil. The need to  secure zero leakage and 100 per cent protection  for personnel is an even stronger imperative at  an offshore operation such as Kashagan, where  sleeping and working quarters are pressurised and  sophisticated emergency evacuation vessels are on- call and on-site 24 hours a day. The need to re-think, re-locate and re-engineer the offshore housing  configuration alone led to an estimated extra $2  billion of costs, but there were other costly mistakes as well.

Once oil starts to flow, some of the associated  gas will be carried ashore by pipeline, processed  and used to power the huge refining complex at  Eskene some 30km north of Atyrau. But the bulk  will be re-injected into the deposit at over 800 times atmospheric pressure. Reinjection is needed to  keep up the high pressure that must be maintained -» to make sure that 9 billion barrels of oil can be  recovered from the field over its lifetime.

All these issues, and others, were thrashed out  during lengthy negotiations. The soul-searching  allowed all sides scope for self-criticism and serious  re-thinking as well as mutual recrimination – but  the freezing of all new contract signing for the  duration of the talks itself added an estimated 30  months of delay to the project. It was probably  worthwhile, however, as the eventual outcome was a radically different organisational plan – and a much greater sense of realism all round.

Invest in Kazakhstan An official publication of the Government of the Republic of Kazakhstan, 2009. Pages: 30-34

PrintFriendly

Tags: , , , ,

Leave a Reply